Garden Museum - Dow Jones Architects

$
0
0

In October 2007 we won an architectural competition to redesign the Garden Museum. The competition brief asked for a new gallery space where temporary exhibitions could be housed in secure and environmentally-controlled conditions.

Dow_jones_mgh_5x4_©david-grandorge_04_large

It appeared to us that creating a dedicated place for the museum’s permanent collection was equally important, as the exhibits were frequently moved to make space for events. We developed a strategy which addressed both issues.

Dow_jones_mgh_©david-grandorge_03_large

Our idea was to create a belvedere within the existing building. This houses the new galleries and provides a raised ground from which a new perspective of the existing building is attained.

Dow_jones_mgh_©david-grandorge_11_large

The belvedere structure enables us to place the temporary gallery at ground floor level and move the permanent collection, from its former location in the nave, up to the new first floor level.

Dow_jones_mgh_©david-grandorge_14_large

This new arrangement also empties the nave of exhibits so that the museum’s diverse cultural programme of lectures, debates and seminars can take place alongside the exhibitions.

Dow_jones_mgh_©david-grandorge_16_large

The belvedere is an entirely free-standing structure that only touches the floor of the existing grade II* listed building and is entirely reversible. The project received whole hearted support from Lambeth planners and English Heritage, who have used the project as an example of how contemporary architecture can successfully meld with historically sensitive buildings.

Dow_jones_mgh_©david-grandorge_20_large

The belvedere is made from Eurban, a pre-fabricated engineered timber material. We used this material as it is light weight and very strong, and allowed us to realise the building forms we required. Being pre-fabricated and made of large panels it is also very quick to build with. The museum was closed for only 12 weeks whilst the work took place, and of this time the structure took three weeks to assemble. The timber structure is also very environmentally friendly.

Dow_jones_mgh_©david-grandorge_22_large

The timber walls are left unfinished so that they recede into the background with the limestone of the church walls and columns, leaving the foreground for the exhibits and the life of the museum.

Dow_jones_mgh_©david-grandorge_24_large

The windows and doors are strongly coloured and protrude through the raw timber walls. The furniture and signage is also strongly coloured and is read as a further layer of detail added to the mute timber form.

Dow_jones_mgh_©david-grandorge_28_large

We also designed the re-hang of the permanent collection. This involved the spatial organization of the exhibition and the design of the cabinets.
From competition win to completion on site was thirteen months. The contract period was twelve weeks. The project cost £300,000.

Dow_jones_mgh_©david-grandorge_37_large

Credits
Structural Engineer: Momentum
Services Engineer: Buro Happold
Lighting Designer: Mindseye
Quantity Surveyors: Pierce Hill
Graphic Designers: Sarah de Bondt
Timber fabricator Eurban

Awards
RIBA Award 2009, Shortlisted
Building Design Magazine Architect of the Year Award – Refurbishment 2010, Winner

Dow_jones_mgh_©david-grandorge_41_large

First_floor_plan_100_a3_large

Ground_floor_plan_100_a3-copy_large

Museum-iso_large

North_elevation_100_a2_large

North_section_100_a2_large

West_elevation_100_a3_large


Viewing all articles
Browse latest Browse all 11324

Trending Articles



<script src="https://jsc.adskeeper.com/r/s/rssing.com.1596347.js" async> </script>